Earthworks are underway on the bypass in the Zelenika neighborhood toward Zeta, with completion expected within a week.
Radoš Zečević, director of Putevi, explained that the section toward the city was completed alongside the main road, and work is now being carried out in the opposite direction toward Zeta. The road is about 800 meters long, and current activities include profiling, widening, and milling.
Zečević emphasized that the project is being implemented to improve traffic safety, as it was previously complicated and dangerous for drivers to merge onto the main road. The new bypass will provide a safer alternative, allowing vehicles to join the main road via the underpass on the right, as well as from the opposite direction.