Work on the ecological reconstruction of the Pljevlja Thermal Power Plant is progressing according to plan and entering its final phase, officials said during a meeting…
Browsing: TPP Pljevlja
As of June 2025, over €44.5 million has been spent on the ecological reconstruction of Montenegro’s Pljevlja Thermal Power Plant (TPP Pljevlja) out of the nearly…
The public consultation on Montenegro’s draft National Energy and Climate Plan (NECP) concluded on Friday. According to the Ministry of Energy, the final report and draft…
The Action for Social Justice (ASP) submitted comments to Montenegro’s Ministry of Energy and Mining on the National Energy and Climate Plan, emphasizing the need to…
The construction of a new over two-kilometer-long riverbed for the Ćehotina River, valued at over €16 million, is a crucial project for the continued operation of…
Energy and Mining Minister Admir Šahmanović stated that there are currently no plans to raise electricity prices for citizens, despite the long-term shutdown of the Pljevlja…
The relocation of the Ćehotina River has prevented the shutdown of the Pljevlja Coal Mine and Thermal Power Plant, securing Montenegro’s energy stability at least until…
The Electric Power Industry of Montenegro (EPCG) is seeking a company to provide expert supervision during the commissioning of the Pljevlja Thermal Power Plant (TPP) following…
Work on the ecological reconstruction of Montenegro’s Pljevlja Thermal Power Plant, which began on April 1, is progressing on schedule toward a planned completion and re-synchronization…
Due to ecological reconstruction works, the Pljevlja Thermal Power Plant (TPP Pljevlja) will be offline from April 1 to November 15. While regular maintenance typically occurs…